Quickly exit this site by pressing the Escape key Leave this site
We use some essential cookies to make our website work. We’d like to set additional cookies so we can remember your preferences and understand how you use our site.
You can manage your preferences and cookie settings at any time by clicking on “Customise Cookies” below. For more information on how we use cookies, please see our Cookies notice.
Your cookie preferences have been saved. You can update your cookie settings at any time on the cookies page.
Your cookie preferences have been saved. You can update your cookie settings at any time on the cookies page.
Sorry, there was a technical problem. Please try again.
This site is a beta, which means it's a work in progress and we'll be adding more to it over the next few weeks. Your feedback helps us make things better, so please let us know what you think.
Freedom of information request reference no: 01.FOI.23.031845
I note you seek access to the following information:
I note a recent FOI request which states the following
- The Command and Control project is within what was called Programme 2 (Optimising Contact and Response) within the Transformation Directorate. (Programme name may have changed)
Can you please state the total payments to the supplier consortium (headed by a company called Leidos) since the project started on or around January 2020.
The MPS response was - From last week, the value of the spend to date with Leidos since January 2020 is £44,205,243.
My question is as follows - Can you please confirm the latest current total payments to Leidos from the same January 2020 date to today’s date (2 August 2023).
I have today decided to disclose the located information to you in full.
Please find below information pursuant to your request above.
- Can you please confirm the latest current total payments to Leidos from the same January 2020 date to today’s date (2 August 2023).
Payments made to Leidos from Jan 2020 to 2 August 2023 are £50,912,569